Countryside Energy intends to develop community-owned windfarms. These will be 10MW initiatives, and take 2-3 years to develop. Until the proposed new Bruce-Milton 500kV transmission powerline is operational (expected 2011), and local distribution upgrades are planned or carried out, we have to wait to plan these projects.

The Co-operative has already collected in excess of 27 months' high-quality wind data at sites near Milverton (Perth County) and Goderich (Huron County) and is well placed to develop these sites.

Updates on progress will be given here as & when they occur.

 